EVM Game Help / Learn EVM

Budget at Completion (BAC)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

The total approved baseline budget for the simulation.

Budget at CompletionBAC = US$54,000What is the planned total budget for the project?
WEEKLY EVM REPORT

Project performance

Earned Value (EV)Calculated
Budget at CompletionYour result

In the game, calculation cards on the weekly report connect the value back to its formula.

🎮 Why this matters in the game

Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.