A ratio that compares earned progress with the progress planned by this point.
Schedule Performance IndexSPI = EV รท PVHow does achieved progress compare with planned progress?
SPI > 1.00Earned progress is greater than the planned position.
SPI = 1.00Earned and planned progress are equal.
SPI < 1.00Earned progress is below the planned position.
WEEKLY EVM REPORT
Project performance
Earned Value (EV)Calculated
Schedule Performance IndexSPI
In the game, calculation cards on the weekly report connect the value back to its formula.
๐ฎ Why this matters in the game
Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.