Variance at Completion (VAC)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

The expected difference between the approved budget and the forecast final cost.

Variance at CompletionVAC = BAC − EACWhat budget variance might remain at completion?
Positive VACForecast completion cost is below BAC.
VAC = 0Forecast completion cost equals BAC.
Negative VACForecast completion cost exceeds BAC.
WEEKLY EVM REPORT

Project performance

Earned Value (EV)Calculated
Variance at CompletionYour result

In the game, calculation cards on the weekly report connect the value back to its formula.

🎮 Why this matters in the game

Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.