Understanding the Simulation

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

The simulation gives you a fixed project baseline and then lets your weekly decisions influence actual progress and actual cost.

Duration12 weeksThe full simulation period.
Scope360 tasks30 tasks planned per week.
BACUS$54,000Approved baseline budget.

When the project ends

You have up to 12 weeks to deliver 360 goods. Reaching 360 accepted goods ends production early at exactly 100%. Before delivery, any excess goods are rejected by a quality inspection as faulty, damaged or below standard. Production costs are retained. Complete the closing week’s EVM report to view the final results. If the target has not been reached, the game still ends after Week 12.

Baseline plan

ItemWeekly plan / rate12-week baseline
Planned tasks30 tasks360 tasks
Planned ValueUS$4,500US$54,000
Planned Resource 1US$1,000US$12,000
Planned Resource 2US$1,000US$12,000
Planned Resource 3US$1,000US$12,000
Project ManagerUS$1,500US$18,000

Why your results change

The baseline remains your reference point. During play, completed tasks determine progress and earned value, while the resources and overtime you use contribute to actual cost. The purpose is to see the trade-off between delivering work and controlling cost.