Estimate at Completion Duration (EACD) forecasts the total project duration in weeks using the current Schedule Performance Index.
Estimate at Completion DurationEACD = 12 / SPIThe planned duration is 12 weeks.
An EACD above 12 weeks indicates a forecast finish behind schedule; below 12 weeks indicates ahead of schedule; 12 weeks indicates on schedule. If SPI is zero, the duration cannot be calculated.