EVEVM GameHelp Centre
Help home
EVM Game Help / Forecasting

Estimate at Completion Duration (EACD)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

Estimate at Completion Duration (EACD) forecasts the total project duration in weeks using the current Schedule Performance Index.

Estimate at Completion DurationEACD = 12 / SPIThe planned duration is 12 weeks.

An EACD above 12 weeks indicates a forecast finish behind schedule; below 12 weeks indicates ahead of schedule; 12 weeks indicates on schedule. If SPI is zero, the duration cannot be calculated.

Still not finding the answer to your question?

Our support team can help. Tell us what you were trying to do and, if possible, include a screenshot of what you see.

support@bridgitafrica.com