Estimate to Complete (ETC)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

The forecast cost required to complete the remaining project work.

Estimate to CompleteETC = EAC − ACHow much more might we need to spend?
WEEKLY EVM REPORT

Project performance

Earned Value (EV)Calculated
Estimate to CompleteYour result

In the game, calculation cards on the weekly report connect the value back to its formula.

🎮 Why this matters in the game

Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.