Learn Earned Value Management, understand the simulation, and find step-by-step guidance for using the EVM Game.

Project duration12 WeeksOne reporting cycle at a time
Planned work360 Tasks30 planned tasks each week
Baseline budgetUS$54,000Budget at Completion (BAC)
Weekly PVUS$4,500Planned value added each week
◈ Learn visually

EVM starts with three numbers

Compare what you planned, what you earned and what you spent. Almost every performance measure in the game grows from these three values.

PROJECT
PERFORMANCE
PVPlanned
EVEarned
ACActual cost
↗ Read performance

Turn numbers into meaning

Use CPI and SPI together. The index tells you the relationship; the trend tells you whether it is changing.

CPI
1.12
SPI
0.84
Example

Cost efficiency can be favourable while achieved progress is still below the planned position. EVM helps you see both at once.

Your 12-week project journey

Every week adds another planned 30 tasks and US$4,500 of Planned Value until the project reaches its BAC.

1W1
2W2
3W3
4W4
5W5
6W6
7W7
8W8
9W9
10W10
11W11
12W12
Start · PV US$4,500Finish · BAC US$54,000

Explore the Help Centre

Start with the concept you want to understand or jump directly to the part of the game you are using.

Start with the three EVM building blocks

Most of the measures in your weekly report begin with three values: what you planned to accomplish, what you actually accomplished, and what it actually cost.

PVPlanned ValueBudgeted value of the work planned.
EVEarned ValueBudgeted value of work actually completed.
ACActual CostWhat the completed work has actually cost.
New to EVM?

Read What is Earned Value Management? first. It connects PV, EV and AC before introducing CPI, SPI and forecasting.