The value difference between achieved work and planned work.
Schedule VarianceSV = EV − PVHow far is achieved work from the planned position?
SV > 0Earned work is greater than planned work.
SV = 0Earned work equals planned work.
SV < 0Earned work is below planned work.
WEEKLY EVM REPORT
Project performance
Earned Value (EV)Calculated
Schedule VarianceYour result
In the game, calculation cards on the weekly report connect the value back to its formula.
🎮 Why this matters in the game
Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.