Reading CPI and SPI Together

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

CPI and SPI answer different questions. Reading them together gives you a more useful view of project performance than either index on its own.

CPISPIWhat the combination indicatesWhat to investigate
> 1.00> 1.00Earned value exceeds both actual cost and planned value.Check whether the performance is sustainable and whether unnecessary cost is being introduced.
> 1.00< 1.00Cost efficiency is favourable, but achieved progress is below the planned position.Look at remaining work, resource capacity and schedule recovery options.
< 1.00> 1.00Progress exceeds the planned position, but actual cost is high relative to earned value.Investigate whether acceleration is costing more than the value it creates.
< 1.00< 1.00Actual cost is high relative to earned value and progress is below the planned position.Review both productivity and cost drivers before adding further cost.
🎮 Your decision still matters

EVM tells you what the numbers are saying. It does not make the management decision for you. Use the indicators together with the project's remaining work, resource options, overtime cost and performance trend.