Estimate at Completion (EAC)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

A forecast of the expected total project cost if current cost performance continues.

Estimate at CompletionEAC = BAC รท CPIWhat might the project ultimately cost?
WEEKLY EVM REPORT

Project performance

Earned Value (EV)Calculated
Estimate at CompletionYour result

In the game, calculation cards on the weekly report connect the value back to its formula.

๐ŸŽฎ Why this matters in the game

Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.