The cost efficiency required on the remaining work to achieve a specified cost target.
To-Complete Performance IndexTCPI = (BAC โ EV) รท (BAC โ AC)How efficiently must the remaining work be performed?
WEEKLY EVM REPORT
Project performance
Earned Value (EV)Calculated
To-Complete Performance IndexYour result
In the game, calculation cards on the weekly report connect the value back to its formula.
๐ฎ Why this matters in the game
Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.