EVM Game Help / Forecasting

To-Complete Performance Index (TCPI)

Learn the concept, see how it is used in the simulation, and understand what the result tells you as the Project Manager.

The cost efficiency required on the remaining work to achieve a specified cost target.

To-Complete Performance IndexTCPI = (BAC โˆ’ EV) รท (BAC โˆ’ AC)How efficiently must the remaining work be performed?
WEEKLY EVM REPORT

Project performance

Earned Value (EV)Calculated
To-Complete Performance IndexYour result

In the game, calculation cards on the weekly report connect the value back to its formula.

๐ŸŽฎ Why this matters in the game

Do not treat this measure in isolation. Your resource choices, overtime, work completed and cumulative cost affect the story told by your EVM results. Use the weekly report and dashboard together before deciding what to change next.